Poole Anderson began working on the McKee Hall renovations at the very end of December. We performed some preliminary work in the attic Spaces near stack B, but our focus throughout this spring will be in Stack A. This month, we are doing demolition work in the bathroom spaces to open them up and prepare for the new construction to create the single use bathrooms. This will create some noise as we have to chip out the existing tile flooring assemblies. Concurrently, we are working in the attic space to transform it into additional student bedrooms. That process begins with removing the insulation to create a safe work space and expose existing electrical conduit that needs to be rerouted before moving on to build up the new flooring assembly. The install of the new flooring assembly consists of installing steel and wood reinforcing before an engineered concrete plank is laid across and covered with plywood. You will likely be able to hear when those materials are installed, but it should only last two weeks.
Follow along for more updates and stay turned for information regarding an upcoming opportunity to tour the space!
Construction is progressing rapidly! All of the bathroom floors recently received concrete infill where the previous tile and setting bed was removed (sorry about that noise!). Now we are able to layout the new floor plan and start framing those walls. We are well underway with this on the lower levels and the electrician, plumber, mechanical, and sprinkler contractors have been busy getting their wiring, piping, and ductwork in place for the initial inspections. Simultaneously, we are working in the attic space to get the new bedrooms built. The walls have been framed and the electrical work is about to begin. We recently completed the welding work required to rearrange the existing steel that extended across the future bedroom windows.
Interested in seeing the space for yourselves? Come join us on March 25th at 4pm to receive a tour of the space, learn more about the project and team and partake in a unique opportunity to sign one of the steel beams!
Layout and bottom track in future bathroom location. markings on slab indicate existing conduit to avoid
New channel steel installed to open up dormer windows
New insulation installed on piping in underground crawl space
Steel set for mechanical pad to prep for future HRU
Wood blocking and plumbing rough ins installed in wall at shower location




Demo of existing walls in progress
Existing bathroom fixtures were broken down to be removed
Existing bathroom tile floor assembly chipped out in prep for future floors
Existing ceiling was removed on the 3rd floor in prep for the new bathrooms
Insulation was removed from floor to allow safe access for welding new steel




